The performance of a full face tunnel boring machine (TBM) in Tarabya (Istanbul)

  • N. Bilgin*
  • , C. Feridunoglu
  • , D. Tumac
  • , M. Cnar
  • , Y. Palakci
  • , O. Gunduz
  • , L. Ozyol
  • *Bu çalışma için yazışmadan sorumlu yazar
  • Istanbul Technical University
  • Tinsa Co.

Araştırma çıktısı: Kitap/Rapor/Konferans Bildirisinde BölümKonferans katkısıHakem

15 Atıf (Scopus)

Özet

The performance of a full face tunnel boring machine (Herrenknecht TBM) was evaluated within the research program of this study. TBM having a diameter of 2.9 m and cutting power of 560 kW was used to excavate the tunnel of 13270 m in length, which was situated between Sariyer and Baltaliman. The main rock formations are Paleozoic aged sedimentary rocks, limestone, sandstone-siltstone, andesite dykes and sediment fillings. The project was commissioned to Tinsa - Öztaş - Hazinedaroǧlu - Simelko consortium. The performance of TBM was recorded continuously for detailed shift analysis. A limestone block having dimensions of 0.4 × 0.5 × 0.4 m, representing majority of the rock formations was collected from one of the shafts. This rock block was subjected to full scale instrumented laboratory cutting tests using a disc cutter taken from the TBM. The relationship between thrust force and depth of cut was compared to the one obtained in the field. It is concluded that accumulated data and instrumented full scale rock cutting tests may serve as a valuable tool to predict the performance of full face tunnel boring machines in any type of rock formation.

Orijinal dilİngilizce
Ana bilgisayar yayını başlığıUnderground Space Use
Ana bilgisayar yayını alt yazısıAnalysis of the Past and Lessons for the Future - Proceedings of the 31st ITA-AITES World Tunnel Congress
Sayfalar821-826
Sayfa sayısı6
Yayın durumuYayınlandı - 2005
Etkinlik2005 ITA-AITES World Tunnel Congress and 31st General Assembly - Istanbul, Türkiye
Süre: 7 May 200512 May 2005

Yayın serisi

AdıUnderground Space Use: Analysis of the Past and Lessons for the Future - Proceedings of the 31st ITA-AITES World Tunnel Congress
Hacim2

???event.eventtypes.event.conference???

???event.eventtypes.event.conference???2005 ITA-AITES World Tunnel Congress and 31st General Assembly
Ülke/BölgeTürkiye
ŞehirIstanbul
Periyot7/05/0512/05/05

Parmak izi

The performance of a full face tunnel boring machine (TBM) in Tarabya (Istanbul)' araştırma başlıklarına git. Birlikte benzersiz bir parmak izi oluştururlar.

Alıntı Yap