ALISS: Advanced Linear Scheduling System

  • Onur B. Tokdemir
  • , David Arditi*
  • , Cenk Balcik
  • *Bu çalışma için yazışmadan sorumlu yazar

Araştırma sonucu: Dergiye katkıMakalebilirkişi

36 Atıf (Scopus)

Özet

The line of balance (LOB) method is not widely used in the construction industry even though it has distinct advantages in repetitive construction projects. Attempts were made in the past to develop LOB systems but no system has met with universal acceptance because of a multitude of problems. As a response, a tool named ALISS was developed that solves most of the problems associated with LOB applications. ALISS is an acronym for Advanced Linear Scheduling System and makes use of a model that utilises the tools of information technology to the fullest extent. This is accomplished by creating a system that has a standalone and a web-based version. ALISS is programmed using Visual Basic and Visual Basic Script languages. It utilises MS Access and SQL server as a data repository. The resulting Advanced Linear Scheduling System not only accommodates all LOB requirements but also provides the latest technological developments as an embedded tool.

Orijinal dilİngilizce
Sayfa (başlangıç-bitiş)1253-1267
Sayfa sayısı15
DergiConstruction Management and Economics
Hacim24
Basın numarası12
DOI'lar
Yayın durumuYayınlandı - Ara 2006
Harici olarak yayınlandıEvet

BM SKH

Bu sonuç, aşağıdaki Sürdürülebilir Kalkınma Hedefine/Hedeflerine katkıda bulunur

  1. SKH 9 - Sanayi, Yenilikçilik ve Altyapı
    SKH 9 Sanayi, Yenilikçilik ve Altyapı

Parmak izi

ALISS: Advanced Linear Scheduling System' araştırma başlıklarına git. Birlikte benzersiz bir parmak izi oluştururlar.

Alıntı Yap