Resource leveling in line-of-balance scheduling

Atilla Damci, David Arditi*, Gul Polat

*Corresponding author for this work

Research output: Contribution to journalArticlepeer-review

50 Citations (Scopus)

Abstract

Resource leveling involves minimizing resource fluctuations without changing the completion time of a project. A smooth distribution of resources minimizes logistical problems and results in cost savings. Line-of-balance (LOB) is a resource-based scheduling system that is used in projects that exhibit repetitive characteristics, performs resource allocation as a matter of course, but does not deal with resource leveling. In the past, researchers experienced declines in productivity whenever they leveled resources in different linear scheduling models by adjusting activities' production rates. The objective of this research is to develop a genetic algorithm-based resource leveling model for LOB schedules that does not impact productivity negatively. This model is based on the "natural rhythm" principle, according to which a crew of optimum size will be able to complete an activity in the most productive way. The "natural rhythm" principle allows shifting the start time of an activity at different units by adjusting the number of crews without changing the duration of the activity in any one unit and without violating the precedence relationships between activities. An LOB schedule is established for a pipeline project and is used to illustrate the proposed resource leveling model. It was observed that the model provides a smoother resource utilization histogram. Performing resource leveling in LOB scheduling without sacrificing productivity is the major contribution of the proposed model.

Original languageEnglish
Pages (from-to)679-692
Number of pages14
JournalComputer-Aided Civil and Infrastructure Engineering
Volume28
Issue number9
DOIs
Publication statusPublished - Oct 2013

Fingerprint

Dive into the research topics of 'Resource leveling in line-of-balance scheduling'. Together they form a unique fingerprint.

Cite this